By Abraham Lincolns | Entebbe
Uganda Civil Aviation Authority says it needs Shs30 billion to procure security scanners, fire trucks and
other equipment required to make Kabalega International Airport fully operational and support revenue
generation.
The Uganda Civil Aviation Authority (UCAA) has asked the government to provide Shs30 billion to
procure critical equipment required to make Kabalega International Airport fully operational.
The request was made by Sam Wonekha, the Director of Airports at UCAA, during a monitoring visit to
the facility by Parliament’s Committee on Physical Infrastructure.
Wonekha said the authority developed an equipment procurement plan four years ago estimated at
Shs76 billion, but only Shs32 billion had been released in the previous financial year, leaving a funding
gap that is affecting preparations to operationalise the airport.
He said the additional Shs30 billion would be used to acquire essential equipment, including security
scanners, three fire trucks and other operational tools.
Wonekha urged the government to release the funds in time to enable the authority to meet its
financial obligations once the equipment is delivered.
William Tio, the committee’s vice chairperson who led the delegation, pledged to engage the
government to ensure the funding request is considered.
Meanwhile, David Bitabangoma, the manager of Kabalega International Airport, said construction of a
new passenger terminal had started, with the contractor already on site.
The project, which is being undertaken by Egypt’s Samco National Construction Company at a cost of
Shs232 billion, is expected to increase the airport’s passenger clearance capacity during peak hours from
100 to 1,000.
Margaret Naziwa, the Kagadi District Woman MP and a member of the committee, commended the
progress of construction and urged residents of Bunyoro to position themselves to benefit from
investment and business opportunities expected to emerge around the airport.
Construction of Kabalega International Airport began in 2018, with works undertaken by SBC Uganda
Limited. The first phase has been completed and is expected to be commissioned by President Yoweri
Museveni in January 2027.
The expanded passenger terminal is expected to be completed in March 2027.